Replacing the SCADA system of the chewing gum plant
What Is Implemented:
- Standard control objects for the entire plant have been created
- Developed a new SCADA design while preserving the existing functionality
The project timeline was 2 years, the project was implemented at one plant in Russia and one plant in Europe.
The complexities of the project include:
- Due to the COVID-19 pandemic, all work was done remotely, using local subcontractors
- Lack of a unified programming standard in the factory
Client:
large international confectionery company
Problematics and Inquiry:
- Lack of ability to upgrade the existing system, the inability of the existing system to work on Windows 10 - this system was a stopper in the project of migration to Windows 10
- Lack of a single SCADA standard at the plant
- Availability of different types of PLCs in the plant
Tools:
- Rockwell automation
- KepWare
Economic effects:
- Reduced upgrade time by bringing to a single standard
- Creating the ability to migrate computers to Windows 10